Construction Update

Update July 5, 2018:

Construction continues with final touches being done on the building.  We anticipate being able to occupy the building mid-late July.

 

 

 

 

Construction continues to be on target for an end of May completion.  Construction is moving along at a blurring speed with the building being dried in for the winter to allow progress regardless of the weather outside.  Much of the drywall in complete in the elementary wing and some installation of tile and cubbies has begun.  Framing and drywall continues in the middle school wing.  Exterior brick work continues on the music wing and the exterior finish of the front entrance is under way.  The windows for the cafeteria have been installed.

Soaring Heights PK-8